Our new Sunderland terminal is approaching completion with only final testing and comissioning to complete before our opening event on Monday 26th July in the presence of The Right Worshipful Mayor of the City of Sunderland, Cllr Henry Trueman and Cllr Graeme Miller, Leader of Sunderland City Council.
Our contractors G&B Construction have reached practical completion at our new Sunderland terminal and Balmoral Tanks have commenced building the first of five tanks to be constructed in our phase 1 development.
Piling the tank bases at Youngs Berth in the Port of Sunderland has been completed by our local contractors G&B Construction of Gateshead. Over reinforced concrete 100 piles have been driven down to the granite bedrock to provide strong foundations for the tankbases and bunded enclosure.